Gantt chart

I've finished the Gantt chart, but unfortunately nor @melancon, @Lakomaa or @Costantino & WeMake reviewed their tasks and milestones. I've only included these 2 types in the chart + administrative reports, because with all the deliverables it would have been too much. So I put in what we had, with some myself and Alberto have created.

I think WeMake and SSE should review their timelines: WeMake's Communication task begins after Design is over and Development has started, which is a little late in my opinion.

SSE does survey in months 6-8 which is a little early if you want to involve participants in the conversation. We will only have a lively conversation after Month 8..

Anyway, if you want chages made let me know, of if anybody is using GanttProject I can send the original file.

File: 

Comments

Now done

melancon's picture

@Noemi Sorry for not complying with instructions earlier ... Things are now in order.

Gantt

Lakomaa's picture

Feel free to adjust the time plan for WP3. There is flexibility so I only care about the order od the tasks and the time allocated for each. E.g. if you want to postpone the quantitative survey, please do so. 

@Noemi I modified the WeMake

Costantino's picture

@Noemi I modified the WeMake schedule anticipating as suggested.

 

Recent site activity

Nadia's picture

Nadia has updated the OpenVillage Festival | Memberships wiki page in the The Reef and OpenVillage Coordination groups

Thu, 23/03/2017 - 17:15
Thu, 23/03/2017 - 16:58

Nadia's picture

Nadia has updated the OpenVillage Festival | Memberships wiki page in the The Reef and OpenVillage Coordination groups

Thu, 23/03/2017 - 14:05

Noemi's picture

Noemi has updated the OpenVillage wiki page in the Op3nCare Community group

Thu, 23/03/2017 - 11:45