interior design options

@reef-building

I prepared a draft for the proposal of the ‘contract options for the finishing’.

I want to go through it with the architects on Tuesday, to be sure we’re not telling any incorrect things.

The sentences in red are still to be validated/completed with/by them.

You can find it under the proposal folder of 2024.

If somebody could review it, and for all to give your opinion on the proposal we want to present to the group…

1 Like

Thanks for this Els’! Very clear!
I made a couple of suggestions/comments, but it’s perfect!

2 Likes

Also had a quick look - all good :slight_smile:

@els I had a look at the new version, thanks a lot for doing this! It’s very clear and super helpful!

I don’t have anything to add but some initial questions (not sure if they are for now or for the plenary though):

  • What is “honoraires AR”?

  • Would it be possible to have an estimate of how much more we are talking with option 2? How much more for architects fees? Idem for techniques spéciales, PEB? Is it a difference of a 1000euros per apartment? 10 000?

  • Problème avec sosim: I didn’t quite understand it

  • Option 1: the choice of the finishings has to be made before we have the final estimate at the end of the avant projet?

  • C’est quoi un Rotor et on l’utiliserait pour quoi?? :sweat_smile:

Hi @Sarah

Thanks for reviewing the new version!

  • Honoraires AR = honoraires architectes, as defined in the contract with the architects, they correspond to 10% des travaux. In option 1 it will be 10% on the invoices of the general company. In option 2, it will be 10% on the invoices of the general company + 10% on the several seperate /individual invoices for the finishings.

  • For the estimate: I asked them how much more expensive the price for the technical experts would be. For the other part (extra cost for the finishing) it all depends on the choices made by the reefling. There honoraires are a % of the total cost. In option 1, you will never be able to go for a very expensive finishing (as the choices will be standard), but if in option 2 you want to go for the most exquisite materials, than the invoices will be a lot more expensive. For the DIY’er that wants to do a lot, option 2 will be , e.g. less expensive.

  • Problème avec sosim. I personally don’t think it is a problem. They said it is simple if -for option 2- you stop the Sosim after having finished the casco. They wondered if it would be possible to go further, meaning keeping the Sosim also for the finishing. But they said to go a see a lawyer to figure out how this would work. After talking to Lee a bit, it’s clear for me that we will not go there, the société simple will stop after the finishing of the casco (indicated like that in the Statutes i think), otherwise the société simple will have the responsability to dive into each individual file (24 of them), know it to be able to follow it up. And for me this is a clear ‘no’.

  • Option 1: the choice of the finishings has to be made before we have the final estimate of the end of the avant projet. If we go for one company. For the general company to be able to give a price offer, they will need to know the finishings we choose. (hence the remark: The choice of the finishing has to happen quite fast, at the same time as the call for tender/call for bids for the casco (appel d’offre)). This also means that this phase of the avant projet will take longer than for option 2. (this ‘loss of time’ will be regained later though)

  • Rotor: it’s not a product or machine but a company (https://rotordc.com/). They recuperate materials when breaking down old building,… and they resell these.

1 Like

@reef-building

Referring to this week’s coordination meeting and lee’s post, there are two topics that need to be adressed soonish.

One of them is this topic: what type of contract we want to go with for the finishing. (The other topic is handled in this post)

In this Sunday’s plenary meeting, the goal is to create common understanding and maybe collect some extra questions for the architects.

The second step will be to come to a proposal to consent to. This Sunday’s plenary will indicate what steps will need to follow (survey needed?) and if we can come to a proposal based on this Sunday’s discussion about the topic.

Does somebody feel like taking up the follow-up of this topic so we can come to a proposal to consent to?

ps: if you would prefer an extra TB meeting or moving the TB meeting of December 17th to next week, let me now.

1 Like

Hello @els and @reef-building,

I read the proposal in detail, and to be honest I am not sure I understand why this is even presented as a proposal. It is very well possible that there is something I am missing. In that case it is unclear to me what exactly entails “casco” and what is understood by “finishings”.

From what I seem to understand from the text of the architects though, the Blueprint (or at least the slide deck) says that units will be delivered casco, first of all because we want people on low budgets to have the freedom to keep the price of their finishings as low as possible, and (to some extent) second also because we want to provide everybody with the freedom to choose their finishings, instead of ending up with the typical Cohousing Projects or Trevi apartment (which all look the same).

My request would therefore be to clarify things as much as possible ahead of the plenary (without exhausting ourselves). On top of that my suggestion - given my argument about the Blueprint above and also the fact that this seems to be a bottleneck - would be to write it up in the agenda as a decision for consent to option 2.

Happy to get your thoughts, here or in a quick call.

@reef-building : i am ok to change it to a proposal after all. Don’t know about you…

@Lee: for me for those who are not DIY and want to go cheap, the first option will be less expensive.

My understanding is that there are not many DIY in the group (i think of 2 but i might be wrong), so i assume that option 1 might still be desired for budget reasons (and faster includes also ‘cheaper’) by some people. I am also having concerns for those going for a bridge loan / getting the abattement. I don’t know what the maximum period those people have in mind, but if I would be in that case and i would want to play it safe, i might want to go for option 1.

I also think option 1 might be an extra argument for Oaktree to continue with us, as it will be less costly in comparaison to option 2 for them (and the way i understood it from Sophie, price is at this moment now the biggest issue for Oaktree).

That is for me the reason why it is maybe worthwhile to put this on the table, and more going for a combination of option 1 and option 2 to allow ‘cheap for not DIY’ with ‘freedom of choice’.

2 Likes

@Sarah

answer from the architects on the higher cost of the techniques spéciales, in case of option 2

Pas facile à estimer. Je dirais un supplément de + 10-15% par rapport aux honoraires de base.

So looking at the price offers we have received (and my understanding there is only 1 missing, for the accoustics), we are at 158.220, so an extra 10-15% = an extra 15.822 à 23.733 (and still adding an extra 10 à 15 % for the accoustics)

There is 5,1% of the total budget foreseen for these special techniques, with these 4 (peb, stabilité, sécurité, technique spécial), we are at 2,93% of the budget,

Adding soil samples and land surveyor (2100 and 2600), we arrive at 3,017% of the budget.

If we add another 23733, then we arrive at 3,46 %, so leaving still 1,64% of the budget for accoustics (if that is the only thing missing in this categorie) = 88.560 euro.

My feeling is that the increase of 10 à 15% of the extra cost for the techniques speciales will still fall in the budget foreseen for them in the FS

3 Likes

hi @reef-full , @joannes , @marcelh ,

As an action point linked to topic ‘choice of contract for the finishing’ of tonight’s plenary, here the survey in which you can indicate your choice.

@alberto: i guess you will choose the same option for both your units, so filling it in once is enough.

Please fill in the form by this Wednesday 11/12, 12:00 (noon).

3 Likes

Thanks Els :slight_smile:

You seem to have gotten the process started but I’m happy to help/take over. I can make time in the next three days, but then it will have to wait until the weekend though, so I’m not sure if that helps… But if there’s something else to be done before wednesday I’m happy to help!

2 Likes

i can take up this one. Thanks

2 Likes

hi @reeflings

I would like to come back to something that was said yesterday in the PM.
Related to option one (for the choice of contract for the finishing), @alberto mentionned that option one would need to full the criteria of durability & sustainability.

I can ask the question to the architects, but for me these are quite broad terms to which it is hard to give a simple answer to (a yes or a no)

So my question to the ones for who ‘durability & sustainability’ is a precondition to choose for option 1. What do you understand by it?

  • an interior/finishing (machines/products) that has a certain quality / that doesn’t need to be thrown away after a limited amount of years => is on my list to ask the architects

  • the materials that the products are made off, are from sustainable resources (natural resources like wood/wool/… over mineral resources over oil-based resources) or for which the production process is ecological (no excessive use of energy or resources) => is on my list to ask the architects

  • the origin of materials/products: new products vs recuperated products => This for me doesn’t go together with option 1. That was clearly indicated by the architects

  • the reusability of the products/machines, once they are damaged/broken can they be reused/recycled? (e.g. clay vs plaster) => I can ask the architects, but I would think that e.g. a clay finishing is not seen as a standard option

Any other elements that you categorize under durability/sustainability?

I think if you want to go as sustainable/durable as possible, you need to go for option 2 as you have a larger range of choices/possibilities.

4 Likes

I always imagined that at some point we would need to decide as a group exactly what we mean by ‘durability’ and ‘sustainability’, in order to convey that information to the architects and/or contractors. At which point they try to meet our criteria within the constraints of our budget. For instance, what’s our position on heat pumps, or how negotiable is a flat roof? Perhaps I’m over thinking it, or perhaps that moment has arrived. Having said that, @els I don’t think we need definitive answers to every question for your proposal to move forward. Perhaps just a shared understanding of what’s important in a broad sense at this point…

3 Likes

The way I had pictured it, was for some Team, lets call them “Team Finishings”, to take care of collective negotiation of several items, like e.g. tiles, kitchen and bathroom, but also more fancy things, like e.g. a recirculating shower (i.e. a shower that only uses 30 liters of water, no matter how long you use it). I also thought that one way or another we would gang together and choose the same contractor, yet having individual contracts (hence keeping more control). Or said shorter: the way I pictured it, was that we would pool our forces wherever we can, while maximising individual choices.

For me to be able to consent to the proposal I would like to get more clarity on:

  • Why is it important that we decide this now? (I don’t want to pretend that I understood what was said at the plenary)

  • What do we win by deciding at this moment to collectivise a very big bundle of finishings?

  • What will we have lost in a scenario where right now we decide to only go for casco, and to collectivise certain (or all) finishings at a later moment?

  • If Option 1 goes forward, how will the accounting be handled?

My intuition is that by signing up now it’s not very clear what we win, while it seems to be certain that those who sign up for option 1 will have very limited choices in terms of hard-core sustainability options.

The “option 1 goes faster” argument I would oppose as an argument in favour of a collective option 1. It says that this is beneficial for those with bridge loans. I would say that this also holds for those who are renting, and that we have a collective commitment to (at least make it possible to) finish the construction with the deadline for a bridge loan (i.e. 2 years).

2 Likes

did the architects say why? when you negotiate with “entrepreneurs” or building companies you can always include a clause in the tender saying … we want X % of materials reused. (materiel de reemploi in french)

I’m not sure what you mean here, could you explain again? Thanks!

If all of this isn’t clear than i propose it be put on the agenda of the next plenary and have another clarification round

2 Likes

We also have a meeting planned with the architects next Tuesday (online at 17:30). Another idea is maybe to join the meeting and ask all your questions to them directly.

1 Like

for those interested: the results of the survey: to be found under ‘casco and finishing contract’ under team building folder.

I will ask the architects the extra questions linked to the conditions people put for chosing for option 1

1 Like