I finally found some time to work on the prospectus. Not done yet, but I did get around to one of the two big steps I had in mind, redoing the financial planning (the other is risk analysis).
For this new version, I looked at the simplified budget v7 and the cash flow forecast we presented at the GA. I made the following decisions:
Divide the budget in four macrocategories: land, expertise, construction (casco) and finishings. There is no separate “taxes” category, rather I bundled taxes and administrative costs with the four macrocategories.
Assume an average cost for the finishings of the private units of EUR 900 x m2. The prospectus will obviously report that the final decision will be made by each individual household for their unit.
Assume the following timeline for construction costs: 1/3 of the casco construction happens in 2026, 2/3 in 2027, nothing in 2028. For finishings: nothing in 2026, 1/3 in 2027, 2/3 in 2028. The idea is that construction would begin around mid 2026 and finish two years later.
Do you think it’s defensible? you can see the table here, look at the Aggregating tab.