It’s all +2 months, no?
My last information from the calls was that the whole project is moved back by two months compared to the application’s time plan, due to late signing of the contract. (It’s what I assumed for the current project plan. I had asked you about details before, but sorry for not following up on this again.)
Anyway, my previously intended 2015-01-31 date for a working software installation on edgeryders.eu seems achievable based on current progress. (@danohu is contributing, which is very helpful, and I have the next 6 weeks full-time for this as well after moving to a more quiet place for programming now …)