We received the meeting minutes of the meeting with the commune mid-november (see post) and discussed this briefly with the architects.

The communal tax (taxe sur les bâtisses)

  • Is for 2025 fixed at 3,87 euro/m3

  • Little/no chance to get exonerated from

  • Not clear at this point on what m3 this exactly applies. (The commune hasn’t given a precise answer to the architect’s question). (I guess it will be minimal based on 1941,3 * 2,7 m3 = 5241,51 m3 => cost of 20.285 euro. Sarah estimated it around 30.000: see file mentioned in the first post in this topic)

  • cost not foreseen in the calculation file of the architects

The regional fees

  • Is fixed at 65 euro/m2

  • Decent/some chance to get exonerated from (based on the reaction of the region in the meeting), but only on the condition we continue with Oaktree (4 units minimal) and they fulfull the conditions of ‘logement conventionné’

  • Cost of 126.185 euro foreseen in the calculation file of the architects (based on 1941,3 m2 which is the m2 of logements)